About the Project
This $10,250,000 retrofit of a 450K sf existing warehouse was completed by Marcobay to
meet the specific needs of Amazon for a new sortation facility. Improvements included
completing a re-roof over the existing metal roof to add the necessary R value; modified
63 docks including dock levelers to meet Amazon’s specification; constructed the data
room and 10K sf of office, security and breakroom space; parking lot addition to meet
new capacity and new site lighting for entire truck court and parking; upgraded power
requirements including future expansion and installed warehouse chiller system. These
and additional improvements were completed in just five months to support the new
fulfillment center that came online on the same “go live” date.